Automatic transfer switching is simple in principle and full of detail in practice. The requirement is to move the load from mains to generator and back without ever connecting the two, and without dropping a load that cannot tolerate the gap.

Transfer time

standard contactor-based ATS transfers in 100 to 300 ms; the load sees a break. static transfer switch transfers in a quarter of a cycle but costs far more and generates heat. Most industrial loads accept the break; IT equipment and some process lines do not, and those need a UPS rather than a faster ATS.

Neutral handling

Three-pole or four-pole switching is a decision with consequences. Four-pole switching breaks the neutral and prevents parallel neutral paths, which is required where RCDs are present or where the generator is separately earthed. Three-pole switching is cheaper and keeps a solid neutral reference, but can circulate current through the neutral between sources.

Interlocks and testing

Mechanical interlock plus an electrical interlock, and a test position that allows the generator to be run on load without exposing the mains. Commission the changeover with a real load, not a lamp. The incoming breaker note covers the protection upstream, and the power distribution cabinet can include the ATS with the interlocks tested and recorded.