Forty Vacuum Pump Control Cabinets Delivered to a Packaging Plant
When a packaging plant replaced its central vacuum system it ordered forty control cabinets, each serving six pumps. The panels had to be identical, had to arrive in the order the mechanical installation progressed, and had to be proven before the pumps were connected.
The requirement
Six vacuum pumps per cabinet, 15 kW each, with one pump held as standby. Lead-lag rotation so run hours evened out across the set. Vacuum level held within a band by staging pumps in and out, with a transmitter feeding the controller rather than a simple pressure switch. Dry contacts to the plant SCADA for running, alarm and trip.
Because the plant ran continuously, the cabinets could not all be installed at once. Mechanical installation was scheduled area by area over three weeks, and the electrical package had to follow that sequence rather than the workshop's convenience.
What we built
- Floor-standing steel enclosures, RAL 7035, IP54, with a common base plate so cabinets could be lined up and bolted together on site.
- DOL starting for the 15 kW pumps, with individual overloads and a contactor per pump.
- Controller with run-hour counters, staging logic and a maintenance alarm at a set hour threshold.
- Door-mounted HMI showing pump status, vacuum level and the active alarm, with a trip history page.
- Hand-off-auto selector per pump for commissioning and isolated maintenance.
Testing before delivery
Each panel was function-tested against a simulated 4–20 mA vacuum signal, with the staging sequence exercised through start, hold, add pump, drop pump and standby swap. The rotation logic was checked by seeding different run-hour totals and confirming the lead pump changed as intended. The test sheet recorded the simulated values and the resulting pump states.
The first cabinet was delivered on its own so the plant could verify the sequence against the real pumps before the remaining thirty-nine were packed. That single early panel saved a batch-wide change: the staging hysteresis needed widening once the real vacuum volume was connected, and the adjustment went into the remaining panels before they left the workshop.
The result
Forty cabinets delivered in four shipments over three weeks, in the order the mechanical contractor needed them. Because the wiring schedule, terminal numbering and label positions were kept identical across the batch, the installing electrician worked from one drawing for all forty.