Why Panel Lead Times Move

Column: Company News    Time: 2024-12-01

Every panel quotation carries a delivery date, and most of them are built from a guess. The date is set by whichever of four queues is longest, and the queue changes with the market.

The four queues

Components — breakers, drives and PLCs, where lead times move from two weeks to four months depending on the model and the region. Sheet metal — rarely the constraint unless the shop is full. Paint — a fixed capacity shared across all orders, and the usual hidden constraint. Test bay — the constraint on a large batch, because every panel needs a powered test.

Reading the market

When breaker lead times extend, every panel builder quotes longer dates at the same time, and customers start ordering earlier, which extends them further. builder who tracks incoming orders against confirmed component availability quotes dates that hold; one who quotes from the catalogue discovers the problem at the end of the month.

What to tell a buyer

The date, the component the date depends on, and the date by which the order must be placed to hold it. That is more useful than a shorter date that will slip. The delivery window note covers the promise side, and the stock note covers which parts can be held to shorten it.