Agreeing Delivery Windows That Hold
Delivery date built from component lead times and paint capacity is worth more than a discount. Most late panels are late because the promise was made before the components were checked.
What moves the date
Breaker and drive lead times, which vary from two weeks to four months depending on model and market. Paint line capacity, which is fixed and shared with other orders. Sheet metal capacity, which is flexible. Test bay capacity, which becomes the constraint on a large batch.
How to promise
Quote against confirmed component availability, not against the catalogue's nominal lead time. Where the lead time is uncertain, give a range and the date the order must be placed to hold the earlier end. customer who understands the constraint plans around it; a customer given an optimistic date plans around a date that will not hold.
When it slips
Tell the customer the day it becomes known, with the reason and the new date. Panels that arrive late are a problem; panels that arrive late without warning are a lost customer. The lead time note explains the component side, and the custom control panel quotations state the component lead time the date is based on.