Reading a Cable Schedule Correctly
The cable schedule is the document that connects the panel to the plant, and it is misread on almost every first enquiry. Four columns cause most of the confusion.
Core count and screen
3C + E means three current-carrying cores plus an earth, not four cores with one used as earth. 2P + E means two pairs plus earth, which is a different cable. Screened cable is written as STP, FTP or with an S prefix depending on the customer's convention, and the difference decides whether the screen can be terminated at one end only.
Voltage grade and route
0.6/1 kV for power, 300/500 V for control. The route matters as much as the grade: a cable in a tray with drives is a different installation from one in a dedicated duct, and the derating follows. Where the route passes through a hazardous area, the schedule must say so before the gland type is chosen.
Reading it against the drawing
Every cable in the schedule should appear on the panel drawing and vice versa. Cables that appear in one and not the other are the ones that arrive on site with no terminal. The terminal schedule note covers the panel side, and the custom control panel is quoted against the customer's cable schedule with discrepancies raised before the build.