Five Checks Before a Drive Is Energised
Most drive failures reported in the first week are not failures. They are site conditions the panel could not see from the workshop: wrong supply voltage, a motor turning the wrong way, a control signal wired to the wrong terminal, or a parameter set for a different drive family.
Before the main breaker goes in
Check the supply voltage phase to phase and phase to neutral, and confirm the neutral is not floating. Check the earthing conductor continuity back to the earth bar. Look at the enclosure for transit damage and condensation — a panel that has been in a shipping container for six weeks may have water in the bottom of the door. Confirm the motor is free to turn by hand and that the driven equipment is unloaded.
First energisation
Energise with the motor disconnected and confirm the drive display, the fan, and the DC bus voltage. Check that the control supply is at 24 V and that no fault appears. Then connect the motor and run at low speed with the load disconnected if possible, confirming direction before the coupling goes back on.
What to record
Write down the supply voltage, the motor current at each operating point, the parameter set version and any alarms. That record is the baseline for every future service visit, and it takes ten minutes. The function test note covers the equivalent test done in the workshop, and the VFD control cabinet is dispatched with the parameter list so the site engineer starts from a known state rather than from a default.