The Value of a Sample Panel Before a Batch

Column: Company News    Time: 2024-11-22

One panel built and approved costs less than a batch built to the wrong interpretation of a drawing. The sample is not a marketing exercise; it is a design review that happens to be physical.

What the sample proves

That the enclosure size is right for the components, that the layout is workable for the wiring, that the terminal arrangement matches the field cables, and that the customer's expectations of finish and labelling match what the workshop produces. All four are assumptions until a panel exists.

Cost and time

sample typically costs 1.5 to 2 times a batch unit, because setup is not amortised, and adds one to two weeks. Against that, a batch of sixty panels rebuilt because the door-mounted meters did not fit is a different order of cost.

How to run it

Build the sample to the production drawing, with production tooling and production labelling. Photograph it, test it, and get written approval with any changes listed. Then freeze the drawing. The first article note describes the inspection, and the custom control panel orders above a small batch size are normally quoted with a sample option.