Buying Panels Locally or Importing Them
Importing panels is usually cheaper per unit and sometimes more expensive per year. The difference sits in lead time, service and the cost of the first breakdown.
The obvious comparison
Unit price, freight, duty, and the currency. On a standard panel, an import from a low-cost manufacturing base can land 20 to 35 % below a local build. That is real money and often decides the order.
The less obvious items
Lead time: eight to fourteen weeks including shipping, against four to six locally. Service: a local builder can be on site in a day; an importer is a spare part and a video call. Spares: a locally sourced breaker is available in the city; an imported one is a month away. And the cost of a production stop while waiting.
What tilts the decision
Standard panels in a plant with maintenance capability favour import. Custom panels with process interlocks, or panels where a day of downtime costs more than the panel, favour local. hybrid works well: import the standard distribution boards, build the process panels locally. The lead time note covers the schedule side, and the custom control panel quotation can be compared line by line with a local offer.
