Twelve Pump Control Panels for a Water Treatment Upgrade

Column: Company News    Time: 2025-01-13

Twelve pump control panels left the workshop over a four-month window for a water treatment upgrade in southern China. The plant could not stop, so the panels were commissioned group by group while the old installation kept running.

The problem

The existing controls were a mixture of direct-on-line starters and two variable speed panels installed a decade apart. The upgrade required the new panels to control the same pumps, with the same duty and standby behaviour, but with data going to a new SCADA system that had not been installed yet.

How it was built

Each group of three pumps got one panel with two drives and one direct-on-line standby, a common PLC and an Ethernet port for the future SCADA link. The panels were tested with a simulated field: float switches, pressure transmitters and motor current all fed from a test box in the workshop.

Commissioning ran at night, one group at a time, with the old panel isolated but still connected. Each changeover took about four hours, and the plant ran on the remaining groups throughout.

What made it work

The control interface to the old system was agreed in writing before the first panel was built, and every panel used the same terminal arrangement, so the site electrician learned one panel and repeated it eleven times. The pump control cabinet used for the series followed the same internal layout throughout, and the duty and standby note describes the logic that was implemented.