Duty and Standby Pumps: Changeover Logic

Column: Technical Notes    Time: 2025-05-20

standby pump that never runs is not a standby. It seizes, its seals dry out, and it fails on the one day it is needed. Automatic changeover solves that and protects the plant at the same time.

Changeover logic

Run the duty pump for a set period — a week is normal — then switch to the other pump and make the first one standby. Do the change with the pumps stopped and the sequence restarted, not while both are running. Record running hours per pump so the changeover can be checked against the log.

Failure transfer

If the duty pump trips on overload, start the standby immediately and raise an alarm. Do not attempt a restart on the failed pump: repeating a start on a jammed impeller is how a motor burns out. Two attempts maximum, then lock out and alarm.

Level and pressure interlocks

Changeover must not fight the level control. Keep one controller in charge of start and stop, and use the changeover only to select which pump responds. Two controllers with independent setpoints will cycle the pumps against each other. The level control note covers the setpoints, and the pump control cabinet is built with the changeover timer and the run-hour log included.