A 60-Panel Export Batch in Nine Weeks

Column: Company News    Time: 2024-12-18

Sixty panels, one specification, one vessel. The order was placed in March for a June sailing, and the schedule held — but not without two moments where it nearly did not.

The build

Twelve panels a week over five weeks, then a buffer week before packing. Sheet metal was cut in one run so every enclosure was identical, and wiring followed a single first-article panel that the customer approved by photo report. Each panel carried the same internal layout, so the third panel was faster than the first and the tenth was faster than the third.

Where it nearly broke

Two component deliveries arrived late: the main breakers slipped by eleven days and the drives by a week. The buffer absorbed the breakers; the drives were resolved by air-freighting the first twenty units so the line could keep running on a partial build. The second issue was paint capacity, which was resolved by running a Saturday shift for two weeks.

What made it hold

The customer approved the first article in three days, the packing specification was agreed before the first panel was finished, and the loading plan was written two weeks before the vessel. The container loading note covers the shipping side, and the custom control panel batch production follows the same first-article discipline.