Second Assembly Shift Added to the Wiring Bay
Wiring bay went to two shifts this month. Same floor space, same test rig, about 60 per cent more panels per week once the handover practice settled.
Why a second shift rather than more floor
The constraint was not space. Sheet metal and coating both had capacity, and the test rig was idle half the day. Wiring and assembly were the bottleneck: every panel passes through the same bay, and the bay ran 08:30 to 17:30 with an hour of overtime when orders were tight.
Adding a second shift uses equipment that was already paid for. Adding a second bay needs building work, another test rig and another set of tools, for the same throughput gain. The second shift is also reversible if demand falls, which a new building is not.
How the handover works
Half-finished panels are where two-shift working usually goes wrong. Panels stopped mid-wiring by one team and continued by another are where the wrong core lands in the wrong terminal.
Rules we put in place before the first evening shift:
- No panel is left mid-circuit. Work stops at a circuit boundary — all of the drive section, or all of the control section — never in the middle of a loom.
- One handover sheet per panel: circuits complete, circuits in progress, components fitted, deviations from the drawing.
- Labels fitted as the wire is pulled, not at the end of the panel. The evening shift cannot label a loom it did not run.
- First hour of the evening shift overlaps the day shift, so questions are asked face to face.
After six weeks the deviation rate settled at what day shift alone produced, which is the measure that mattered to us.
What changed in the workshop
- Lighting. The bay was lit for daylight. Added task lighting over each bench — wire identification at 21:00 in a dim bay is how mislabelled cores happen.
- Tooling. Second set of crimpers, stripping tools and torque screwdrivers, so nothing waits at a shared bench.
- Test rig scheduling. Rig booked by panel, day and evening, with the last evening slot left free for rework.
- Material staging. Components kitted per panel the afternoon before, so the evening shift starts with a complete kit rather than a walk to stores.
Effect on lead time
| Measure | Single shift | Two shifts |
|---|---|---|
| Panels wired per week | 9 – 11 | 15 – 17 |
| Typical lead time, standard cabinet | 18 – 22 working days | 12 – 15 working days |
| Overtime hours per week | 14 | 4 |
Lead time did not fall by the full 60 per cent because engineering and sheet metal did not double, and they are now the constraint on custom work. That is the next thing to look at, not more wiring capacity.
What we are watching
Two-shift working converts a capacity problem into a supervision problem. The evening shift runs with one team leader rather than the day shift's two, and the people on it are the same wiremen rotating week to week rather than a separate crew. Rotation keeps drawing knowledge shared; a permanent night crew would have drifted within a year.
Second watch point is quality at the boundary. We audit the first panel completed after each handover against the drawing, in addition to the normal final test. Nothing has come out of it yet, and the audit stays in place.