Handling Non-Conformance Without Delay

Column: Technical Notes    Time: 2025-02-22

Raised non-conformance that waits a week for an answer costs more than the rework. The panel sits, the batch stalls, and the delivery date moves while everybody waits for a decision that takes ten minutes to make.

Who decides

Three levels: the shop supervisor for cosmetic issues and minor deviations within the drawing tolerance; the engineer for anything affecting function; the customer for anything affecting the agreed specification. Define the thresholds before the batch starts, not during it.

How fast

Same day for levels one and two. Level three within two working days, with a stated default action if no answer arrives — normally "proceed to drawing, note the deviation". default protects the schedule without pretending the customer agreed.

Closing it

Record the non-conformance, the decision, who made it and what was done. closed record is what turns an incident into a process improvement; an email thread is what turns it into an argument six months later. The punch list note covers the end-of-batch equivalent, and the custom control panel builds carry a non-conformance log with the delivery documents.