Annual Quality Audit Completed With No Major Findings

Column: Company News    Time: 2025-09-16

Annual external quality audit closed last week with no major findings and four minor observations. The audit covered incoming inspection, wiring records and the test log for every panel shipped in the previous twelve months.

What the auditor looked at

  • Incoming inspection. Records for a sample of components received, matched against purchase orders and certificates of conformity.
  • Traceability. For three shipped panels, the full chain from customer order through drawings, component batches, wireman, test sheet and packing list.
  • Test records. Every panel's test sheet, checked for completeness and signature, and cross-checked against the shipping date.
  • Non-conformance handling. What happened after each reported defect in the period, and whether the corrective action was verified.
  • Calibration. Torque tools, insulation tester, multimeters — certificates current and instruments identifiable.

The four observations

None of them stopped a shipment; all four are being closed out before the next audit.

  • Storage segregation. Rejected components and production stock shared a shelf, separated by a label. Now separated by a physical barrier and a red floor marking.
  • Legibility on two test sheets. Values written in a way that required interpretation. The sheet has been redesigned with boxes for the recorded value instead of a free line.
  • Revision control on one drawing. Two revisions in circulation for the same panel number, one of them a red-line copy that had not been superseded. Red-line copies now carry a dated stamp and are destroyed at as-built issue.
  • Supplier evaluation. One new supplier had been used before the evaluation record was signed. The process was correct, the sequence was not.

What the audit confirmed

Traceability held up on all three sampled panels, including one shipped eleven months earlier. The auditor traced a specific contactor batch to the panel it went into in under ten minutes, which is the practical test of whether a traceability system works or merely exists.

Test records were complete for all panels in the period. That sounds like a low bar until you consider what it means: no panel left the workshop without four tests recorded and signed. In our first audit six years ago, the gap was around 8 per cent.

Where we are still weak

Two areas we flagged ourselves before the auditor did.

First, the corrective action loop closes slowly on supplier issues. Components that arrive out of specification are handled immediately for that batch; the conversation with the supplier about the next batch takes weeks, and in the meantime ordering continues.

Second, drawing revision discipline depends on one person. The system works because the drawing controller is careful, not because the process is impossible to bypass. That is a single point of failure and it is being fixed with a controlled issue register rather than more training.

What this means for customers

Nothing changes in what we ship. The value of an audit is in what it forces you to look at: three panels traced end to end, four observations that were all process sequencing rather than product quality, and a documentation system that is now slightly harder to bypass.

Customers who require a copy of the certificate or the audit summary for their own supplier records can request it through the contact page. The certificate is also listed on our product certificate page along with the test standards we work to.