Crating and Container Loading for Export Panels
Sea freight is a vibration test nobody schedules. Six weeks of small-amplitude shaking, two crane lifts, a container floor that flexes, and a humidity cycle that condenses water inside anything sealed. What goes inside the crate decides whether the panel arrives as it left.
What actually fails in transit
In our claim history, four items account for almost everything:
- Door hinges and locks, from the door swinging against its stops under vibration.
- Loose DIN-rail devices and relay bases, from clips that were seated but not locked.
- Screw terminal connections that were torqued but not re-checked after the panel was moved by forklift.
- Paint damage at corners and edges, from the crate itself.
Wiring faults are rare. Mechanical movement is the problem.
The crate
Panels travel in a plywood crate on a timber skid, not in cardboard and stretch film. Our standard build for a floor-standing cabinet:
- Skid with bearers spaced to suit a forklift and a pallet truck, sized to the cabinet footprint plus 100 mm.
- Panel bolted to the skid through the base plate, not strapped — straps loosen as timber dries.
- Polythene bag over the whole cabinet with a desiccant sachet, sealed at the base.
- Edge protection at all four vertical corners and along the top front edge.
- Plywood crate walls, with the lid screwed rather than nailed so customs can inspect and re-close.
- ISPM 15 heat-treated timber throughout, stamped, because untreated packing is refused at most borders.
Height matters as much as strength. Crates taller than they are wide need diagonal bracing, or they arrive leaning.
Inside the panel during transit
- Doors closed and the lock taped, plus a transit bracket on large doors so the hinges carry nothing.
- Loose items — drawings, spare fuses, keys, test sheet — in a bag fixed inside the door, never loose in the cabinet.
- Heavy removable modules (drives above 15 kW) shipped separately in their own carton, or bolted to the mounting plate with transit screws.
- Terminal covers left in place; they also stop anything falling onto live parts during installation.
Container loading
Twenty-foot container holds four floor-standing cabinets of 800 × 600 mm side by side with the doors facing the aisle, or six if the doors face each other in pairs. Loading plan matters for two reasons: weight distribution, and whether the first panel out is the one the site needs first.
Practical notes:
- Heaviest crates at the container floor over the skid beams, lighter ones stacked no more than two high.
- Air bags or timber battens between crates so nothing shifts against a neighbour.
- Nothing stacked on a crate lid unless the crate was designed for it — the lid is not a load-bearing surface.
- Photograph the loaded container with the door open before closing. It settles arguments about who loaded what.
Documents that travel with the goods
Packing list per crate, with the panel serial numbers and a weight per crate. Drawings and test sheets in a document pocket inside the door, and a second copy in the crate. Customs paperwork in a pouch on the outside of the crate, in a waterproof sleeve — a wet commercial invoice delays a shipment as effectively as a missing one.
After arrival
Two habits worth passing to the receiving site: inspect the crate before signing the delivery note, and photograph any damage before unpacking. Once the crate is opened, the carrier's liability is essentially over.
On arrival, before energising: check for condensation inside the enclosure, verify terminal torque on a sample of connections, and confirm that no device has come off its rail. Ten minutes that prevent a first-day failure.
For orders that ship with a spare parts kit, the kit travels in its own labelled carton on top of the load, not buried behind the last cabinet. Details like that decide whether the kit is found in week one or in year two.