Drawings a Panel Shop Needs Before Cutting Steel

Column: Technical Notes    Time: 2025-12-16

Half the questions we ask at enquiry stage are not about the panel. They are about the information needed to build it, and each one changes either the price, the lead time or both.

What we ask for before quoting

ItemWhat it changes
Single-line diagramBoard structure, protection, metering, busbar rating
Motor list with kW, current, dutyDrive sizing, starter type, cable and overload selection
I/O list or control philosophyPLC size, terminal count, enclosure height
Supply voltage, frequency, fault levelBreaker breaking capacity, busbar, clearances
Site environmentEnclosure material, IP rating, cooling
Interface to plantProtocol, hard-wired signals, SCADA points

Where some of these are missing, we quote with a stated assumption and mark it on the drawing. That is workable. What is not workable is a quote built on silence, because the assumption then becomes a variation.

Drawings we produce and what they are for

  • Approval drawing. Layout, enclosure size, door arrangement, entry positions, main component positions. Issued before steel is cut, for customer comment. Changes are free at this stage.
  • Schematic. Circuit by circuit, with wire numbers. Issued with the approval set so the control philosophy can be checked.
  • Terminal schedule. Every field terminal, its wire number and destination. The document the installing electrician actually works from.
  • As-built set. The above, revised to what was built, delivered in the door pocket.

The three questions that cost the most when answered late

Where do the cables enter? Bottom entry versus top entry changes the gland plate, the internal duct run and the position of the terminals. Asked after the enclosure is ordered, it becomes a modification.

How much spare capacity? Spare terminals, spare DIN rail, spare gland positions, spare panel width. Buyers who answer "some" get the minimum. Buyers who say "20 per cent spare terminals and one spare 100 mm of DIN rail per strip" get a panel that a future project can extend.

Who signs off the drawing? On a project with a consultant, an end user and a contractor, approval can circulate for weeks. Naming the single approver at enquiry stage is worth more to the schedule than any workshop efficiency.

What can wait

Not everything is needed on day one. These can arrive after the order is placed without affecting the build:

  • Cable schedule, provided entry positions and gland sizes are known.
  • Terminal numbering convention, if the customer has one. Default is destination-based numbering, which suits most plants.
  • Label language, where a bilingual panel is required.
  • Paint colour, until the shell goes to the coating line.

Working with DWG and PDF files

Either is fine, and a phone photograph of a marked-up printout is often more useful than a polished CAD file that has not been checked. What matters is that the drawing states the version, the date and what changed from the previous one. Two undated revisions in circulation is how a panel gets built to the wrong one.

Where a buyer has an existing standard — a numbering scheme, a preferred brand list, a terminal marker format — send it at enquiry stage and we will follow it. Matching a plant's existing practice is cheaper than teaching the maintenance team a new one, and it is the single most useful document in the package.