Rewiring a Textile Mill Line in Six Weeks

Column: Company News    Time: 2025-01-11

textile mill in Zhejiang needed a full line rewired after a fire in a control room. The line produced for export orders with fixed shipment dates, so the requirement was a rebuild that never stopped production for more than a weekend.

The constraint

The line ran 24 hours, six days a week. Stopping it for a week would have cost more than the panels. The old drawings were partly missing, and the remaining sheets did not match the panel as built.

Approach

The first step was a survey: every terminal photographed, every device identified, the drawing corrected before anything was designed. The new panels were then built as a like-for-like replacement with the same field terminal numbering, so the existing field cables could be transferred one at a time.

Transfer happened over five weekends. Friday night isolate and strip, Saturday install and terminate, Sunday test and hand back. The first weekend took eighteen hours; the fifth took eight.

Result

The line lost no production days, and the plant ended with drawings that matched the installation. Where the original control used mechanical timers, those stayed mechanical — the brief was replacement, not modernisation. The custom control panel route suits this kind of work, and the legacy PLC retrofit note covers the survey stage in detail.